What Scope Creep Cost Calculator does, with a checked example
Scope creep is work added after a project is agreed, and it rarely bills at the rate the original estimate assumed. This calculator turns every change request into money: log each request with its additional hours and an hourly rate, and it accumulates the added cost against your original budget, reporting the overrun as a dollar figure and a percentage. A dashboard compares the original and projected final budgets side by side. The most common mistake is entering only direct labor: the total is exactly what you type in, so hours spent on rework, retesting, and client review stay invisible unless you log them too.
Worked example
A concrete input and expected output from the current implementation.
Input
Original budget: $10,000. Three change requests, each adding 10 hours of work at a $100/hour blended rate.
->
Expected output
Added cost: $3,000 across 3 requests. Overrun: 30% of the original budget. Projected final cost: $13,000.
Each request prices at 10 x $100 = $1,000; the three requests sum to $3,000, which is 30% of the $10,000 baseline; adding the creep cost to the baseline gives $13,000. Every figure follows directly from the inputs.