What Project Timeline Planner does, with a checked example
A project plan is a list of dates until it is drawn on a calendar. This tool takes the phases, milestones, and dependencies you enter and lays them out on a shared timeline axis, with swim lanes grouping work by person or team. It converts your start and end dates into spans on that axis, so what you read back is the shape of the schedule: where phases overlap, where they touch, and what must finish before what. The most common surprise is that a milestone is a point, not a bar: it carries no duration and marks one date. The plan stays in your browser; nothing is uploaded.
Worked example
A concrete input and expected output from the current implementation.
Input
Discovery: start 2026-03-02, end 2026-03-13, lane Alice
Milestone M1 (requirements frozen): 2026-03-13
Build: depends on M1, end 2026-04-03, lane Bob
->
Expected output
Discovery renders as a bar from Mon Mar 2 to Fri Mar 13, 2026: 10 business days, in Alice's lane. M1 sits as a marker on Fri Mar 13, at the end of Discovery. Build cannot start before M1, so it begins Mon Mar 16, the next business day, and runs to Fri Apr 3, 2026: 15 business days, in Bob's lane. The two bars do not overlap.
March 1, 2026 falls on a Sunday, so the 10 business days from Monday March 2 end on Friday March 13, and the next business day is Monday March 16. Fifteen business days from March 16 end on Friday April 3. Both spans follow from the entered dates plus the dependency, which forces Build's start after M1.