Line items and earned value
Each line item carries a budget, an actual amount, and a percent-complete figure. The tool sums budgets and actuals across items and computes each item's variance, then converts percent complete into earned value per item by multiplying budget by completion. Earned value totals feed the cost variance (EV minus AC) and the cost performance index (EV divided by AC), which normalizes overruns across projects of different sizes.